- Trail:
- Dave's Line (Hartland Mountain Bike Park)
- Status:
- All Clear / Green
-
Issue status:
- Condition:
- Wet - wet & tacky, likelihood of mud, be kind to trails
- Reporter Primary Activity:
- Mountain Bike
Description:
Filled bottom portion of rock work on alt route.
Installed trail between the two large boulders towards the north side of the Alt route (see pic)
Installed trail between the two large boulders towards the north side of the Alt route (see pic)
- Work Report:
- trail work done
- 1 volunteer attendees
- 4 volunteer hours
- 1 total workers
- 4.0 total work hours
Individual Workers:
SIMBSTrailsDirector
SIMBS Apr 15, 2017 at 21:40