Large fallen tree was removed on 4-2-18 at the bobsled section. New line option being worked on after the mid way rock garden to drop. New option veers riders left (descending). Curve into the drop, and curve after landing. Feature isn't finished yet, dirt needs packed in on and around the rock work.
  • trail work done
  • 6 volunteer hours
  • 2 attendees
  • 12 total work hours

Previous Reports

statusdatedescription
Apr 18, 2018 @ 6:22am
Apr 18, 2018
Muddy and some water on trail. Should dry up over the next few days view
Apr 9, 2018 @ 8:09am
Apr 9, 2018
Trail has been raked from top to bottom. Middle rock garden has numerous additions. New line, new drop and a new kicker over the creek. (all... view
Mar 30, 2018 @ 8:24am
Mar 30, 2018
Large tree down across trail, blocking trail Immediately after the bobsled section near the top. Its down on the bench cut before the chute. ... view