- Trail:
- St. Margarets Bay Trail (Tantallon)
- Status:
- Minor Issue / Yellow
-
Issue status:
- Condition:
- Variable - some wet spots, or some dusty spots but overall good conditions
- Reporter Primary Activity:
- Mountain Bike
Description:
https://www.facebook.com/smbarta/posts/pfbid0Nxb45GcAsv5txELSUdHYg1oKvjc3zAtKSm9edoDnCzbJjZsMjgsLik4bbDHhUY2Dl
"We have gotten approval for the following in our re-opening plan , and while many are still recovering from the impact from the storm , many trail groups are navigating the major implications to the effects of the storm .
So here is what SMBRTA has proposed and was approved by the Dept this morning.
1. Hubley start of SMBRTA will open to Station Rd in Head of St Margaret’s Bay.
2. Island View Dr to Hubbards will re-open
The reopening time is 6 pm tonight !!!
⚠️Island View Dr to Station Rd At the Head of St Margaret’s Bay will remain closed , this received the most impact , there are many people involved including engineers, contractors as well as the Dept . This area will be a long closure until it’s repaired, inspected and safe for all trail users."...
"We have gotten approval for the following in our re-opening plan , and while many are still recovering from the impact from the storm , many trail groups are navigating the major implications to the effects of the storm .
So here is what SMBRTA has proposed and was approved by the Dept this morning.
1. Hubley start of SMBRTA will open to Station Rd in Head of St Margaret’s Bay.
2. Island View Dr to Hubbards will re-open
The reopening time is 6 pm tonight !!!
⚠️Island View Dr to Station Rd At the Head of St Margaret’s Bay will remain closed , this received the most impact , there are many people involved including engineers, contractors as well as the Dept . This area will be a long closure until it’s repaired, inspected and safe for all trail users."...