• Trail:
  • The Hill Loop (Calvin Crest Camp)
  • Status:
  • All Clear / Green
  • Issue status:
    Assigned user:
  • Condition:
  • Ideal - Hero dirt! Not wet but not dry, moisture in soil.
  • Reporter Primary Activity:
  • Mountain Bike
Description:
Storm Clean-up: Cleared remaining tree blockage on Switchback Trail and Hill Loop. All blockages from the storm are now cleared except for large cut-up tree sections in the 5 Bridges ravine.
  • Work Report:
  • trail work done

  • 1 volunteer attendees
  • 4.5 volunteer hours
  • 1 total workers
  • 4.5 total work hours
Individual Workers:
hshear (Howard Shear)
hours: 4.5
paid: no

Previous Reports

statusdatedescription
Sep 26, 2025 @ 4:55pm
Sep 26, 2025
DIRT: The Hill Climb is really washing out and exposing the roots big time. view
Jul 26, 2025 @ 3:18pm
Jul 26, 2025
7/26/25 THOR Trail Day Mowed and String Trimmed most of the trail. Several down trees were removed. Many face slapers and eye pokers trimmed back... view