Trimmed back Mill Road loop before, after and to the Mill Rd. lot.
  • Work Report:
  • trail work done

  • 2 volunteer attendees
  • 2 volunteer hours
  • 2 total workers
  • 2.0 total work hours
Individual Workers:
Nedermeyer
hours: 1
paid: no
anonymous
hours: 1
paid: no

Local Weather During Report

  • Summary
    Cloudy
  • Temperature
    20° (19°/22°)
  • Precip
    0.07 mm/h
  • Wind
    6.04 km/h
  • Cloud Cover
    100%
  • Humidity
    0.87

Previous Reports

statusdatedescription
Aug 25, 2026 @ 1:03pm
Aug 25, 2026
Rode all but Wild Turkey 1 and 2 because of time constraints. Removed all large deadfall blocking trail. Removed downed tree on Loop 5. A lot of... view
Aug 21, 2026 @ 12:02pm
Aug 21, 2026
Put in new signage and closed the old entrance. view
Aug 20, 2026 @ 2:10pm
Aug 20, 2026
Entrance from Mill Rd parking lot was moved 20 feet west from the now old blocked entrance. The tree was 3 feet thick with 2 trunks. Unable to cut... view