- Trail:
- Orange Trail (Mercer County Park)
- Status:
- All Clear / Green
-
Issue status:
- Condition:
- Ideal - Hero dirt! Not wet but not dry, moisture in soil.
- Reporter Primary Activity:
- Mountain Bike
Description:
AD Hoc TM 9/9/26 TAS 2.5 hours
Removed the large tree on Orange trail below the dam plunge pool that was reported and previously worked on 9/7/26 by Al and Ron.
It was quite the challenge to safely cut and move the remains off the trail bed.
Beautiful afternoon breeze in the woods.
On the walk out I met a box turtle!
TAS
Removed the large tree on Orange trail below the dam plunge pool that was reported and previously worked on 9/7/26 by Al and Ron.
It was quite the challenge to safely cut and move the remains off the trail bed.
Beautiful afternoon breeze in the woods.
On the walk out I met a box turtle!
TAS
- Work Report:
- trail work done
- 1 volunteer attendees
- 2.5 volunteer hours
- 1 total workers
- 2.5 total work hours
Individual Workers: