• Trail:
  • Ridgeback – R3 (Station Flats)
  • Status:
  • All Clear / Green
  • Issue status:
    Assigned user:
  • Condition:
  • Dry -
  • Reporter Primary Activity:
  • Mountain Bike
Description:
More work on the eroded root drops at the south end of the ridge.
  • Work Report:
  • trail work done

  • 2 volunteer attendees
  • 12 volunteer hours
  • 2 total workers
  • 12.0 total work hours
Individual Workers:
HankmOgqJb (Hank Kauffmann)
hours: 6
paid: no
murraysagal (Murray )
hours: 6
paid: no

Previous Reports

statusdatedescription
Oct 1, 2026 @ 5:35pm
Oct 1, 2026
Continued working on the eroded root drops at the south end of the ridge just above the berms. view
Sep 29, 2026 @ 5:58pm
Sep 29, 2026
Repairing eroded root drops at the south end of the ridge just above the berms. view
Aug 28, 2026 @ 4:46pm
Aug 28, 2026
view

1 Comment

  • + 1
 Murray I had an awesome day, it was very satisfying.





  • 1
  • Share with followers