- Trail:
- Reid Divide (Tally Lake Area)
- Status:
- All Clear / Green
-
Issue status:
- Condition:
- Dry -
- Reporter Primary Activity:
- Mountain Bike
Description:
All clear as of June 2, 2021! On 6/02, FAMB Trail Crew finished clearing the entire trail of obstructions from the upper trailhead at Bill Creek FS 2942 to Tally Lake Rd. In total about 65 trees, not including cutbacks and overhang. The crew also brushed the lower ~2 miles to improve ride-line visibility, maintained drainage, and undertook several tread repair projects. As always, conditions change rapidly so keep an eye out for trail obstructions. Enjoy!
- Work Report:
- trail work done
- 4 paid attendees
- 120.4 paid hours
- 4 total workers
- 120.4 total work hours
Individual Workers:
anonymous
hours: 30.1
paid: yes
anonymous
hours: 30.1
paid: yes
anonymous
hours: 30.1
paid: yes