• Trail:
  • Design Windows Easy Down (Signal Hill)
  • Status:
  • All Clear / Green
  • Issue status:
    Assigned user:
  • Condition:
  • Variable - some wet spots, or some dusty spots but overall good conditions
  • Reporter Primary Activity:
  • Mountain Bike
Description:
moved tralier etc to lower pile plus checked out how the new gravel was draining all seemed ok
  • Work Report:
  • trail work done

  • 1 paid attendees
  • 2 paid hours
  • 1 total workers
  • 2.0 total work hours
Individual Workers:
craiggoesmountainbiking
hours: 2
paid: yes

Previous Reports

statusdatedescription
Jul 3, 2026 @ 11:12pm
14 hours
gravel work. 60m today . Jason came and help in the afternoon view
Jul 3, 2026 @ 11:11pm
14 hours
gravel work did about 30m. view
Jul 1, 2026 @ 11:26pm
3 days
gravel work. putting in new drain and prep view

0 Comments






Official Trail Reporter i

  • MBO - Reporter Group
  • MBO Trail Crew
  • 0
  • Share with followers